On January 9, 2026, Oklo and Meta announced an agreement supporting development of a nuclear-energy campus in Pike County, Ohio capable of scaling to 1.2 GW.
The project is intended to support Meta's growing Ohio data-center operations, including AI infrastructure.
The current planned schedule is:
| Milestone | Target |
|---|---|
| Pre-construction/site work | 2026–2027 |
| General construction | Early 2028 |
| First-phase operation | 2030 |
| Full 1.2 GW buildout | 2034 |
The most important clarification is:
Meta is not currently receiving 1.2 GW from operating Oklo reactors. The agreement supports development of a future phased nuclear campus.
AI workloads require large computing clusters.
Those clusters require:
For hyperscalers, the challenge is not merely buying renewable-energy certificates. They increasingly need new physical power generation that can support long-duration, high-load operations.
Nuclear power can potentially provide:
Advanced-reactor developers argue that smaller units can also be deployed closer to large industrial or computing loads.
Oklo says the agreement provides a mechanism for Meta to:
Oklo plans to use this funding to secure nuclear fuel and advance Phase 1.
This is more economically meaningful than a simple statement that the companies are “exploring nuclear.”
Nuclear projects require substantial capital before revenue begins.
A customer that provides early money can potentially help with:
That may reduce part of the funding burden that would otherwise fall on equity investors.
Oklo's disclosed model remains centered on Oklo developing and operating its own powerhouses.
The agreement is structured around the supply of future power rather than Meta simply purchasing a reactor from Oklo.
1.2 GW equals:
1,200 MW
With current Aurora units designed around 75 MW each, a full-scale campus represents a large multi-unit deployment. Oklo's project materials refer to a 16-unit site when discussing staffing.
Oklo controls more than 200 acres in Pike County at the former Portsmouth Gaseous Diffusion Plant area.
The site also sits near Centrus' Piketon uranium-enrichment operations, creating potential strategic links between:
Oklo and Centrus announced plans to explore a HALEU deconversion joint venture in Pike County.
Then in June, they signed an LOI under which Centrus intends to supply enough HALEU for multiple years of operation for up to five Aurora units, with deliveries scheduled from 2029.
This links:
Fuel production
↓
Aurora
↓
Meta-supported demand
within the same broader Ohio region.
Not yet.
The June announcement explicitly states that the LOI anticipates negotiation of a future definitive agreement.
Therefore, articles should not say:
“Centrus has guaranteed all fuel needed for the entire 1.2 GW campus.”
That would overstate the current commitment.
Oklo currently targets first-phase operations for the Ohio campus as early as 2030.
Between now and then, important steps include:
The project therefore has substantial execution risk despite the size of the commercial opportunity.
The full 1.2 GW campus is targeted for 2034.
That means investors valuing all 1.2 GW as if it were operating today are ignoring nearly a decade of:
The agreement can potentially improve investors' confidence in:
A major hyperscaler wants future nuclear capacity.
Customer prepayments can support development.
The contemplated campus is far larger than a single Aurora unit.
Success could create a blueprint for other data-center customers.
2030 and 2034 are targets, not guarantees.
Large fleets require large quantities of qualified fuel.
Many repeated units must be manufactured and installed.
Commercial regulatory approvals remain necessary.
Oklo must ultimately deliver electricity at economics acceptable to both itself and customers.
No.
It materially strengthens the commercial story, but future revenue still depends on project execution and the detailed commercial arrangements.
Development funding should not automatically be treated as equivalent to decades of realized electricity revenue.
OKLOON is linked to OKLO.
If the market increases its valuation of Oklo because the Meta campus progresses, OKLO may respond and OKLOON may follow.
But OKLOON does not itself represent:
1.2 GW of Meta electricity capacity.
For the product distinction, read What Is OKLOON?.
Up to 1.2 GW.
Pike County, southern Ohio.
As early as 2030 under the current target.
No.
The agreement includes mechanisms for prepayment and early-stage funding.
The Ohio project remains under development. Its capacity, economics, timing, licensing, financing and commercial structure can change.

Oura's competitors fall into three groups, according to its IPO prospectus: smartwatch makers such as Apple, Google and Samsung; fitness wearables such as Garmin, Coros and Whoop; and software-only

Yes, Oura is profitable on a net income basis. Its IPO prospectus shows net income of $60.8 million on revenue of $1.21 billion in the nine months to June 30, 2026. The $924.3 million loss in some

Bitget scores 3.8 out of 5 on our six-dimension scorecard as of 25 September 2026, leading on derivatives, holding a provisional 3.5 on security after the hot-wallet incident of about $351.6 million

Executive Summary Dell Technologies Inc. (NYSE:DELL) jumped roughly 8% to 10% after hours on September 1, 2026, following a fiscal second-quarter report that blew past Wall Street's expectations The

During crypto market growth cycles, global liquidity often acts as the fuel that drives capital into risk assets. When the amount of money and credit in the financial system increases, investors tend

Overview Bitcoin prices surged aggressively today, breaking above $79,300 intraday and rapidly approaching the landmark $80,000 threshold. Unlike previous speculative rallies characterized by

The U.S. June jobs report signaled a clear economic slowdown, missing expectations and lowering Federal Reserve rate hike fears. Despite lower Treasury yields, AI and tech stocks slid, proving that ma

Goldman Sachs is making its Financial Square Treasury Instruments Fund, known by the institutional share-class ticker FTIXX, available to qualified U.S. participants through Lynq, a real-time settleme

Oura postponed its Nasdaq initial public offering on September 29, 2026, citing uncertainty in the IPO market even though, by its own account, demand for the deal was strong. The IPO has not been canc

Oura's competitors fall into three groups, according to its IPO prospectus: smartwatch makers such as Apple, Google and Samsung; fitness wearables such as Garmin, Coros and Whoop; and software-only he

Yes, Oura is profitable on a net income basis. Its IPO prospectus shows net income of $60.8 million on revenue of $1.21 billion in the nine months to June 30, 2026. The $924.3 million loss in some hea